Case Study: St. Canices Hall, Kilkenny

Introduction

St. Canices Hall is locally used for such activities as boules playing, afterschools facilities, mens club and occasional functions in the community. The hall offers a valuable resource for those wishing to socialise with their community.St. Canices Hall is locally used for such activities as boules playing, afterschools facilities, mens club and occasional functions in the community. The hall offers a valuable resource for those wishing to socialise with their community.

St Canices HallEnergy Efficient Lighting

St. Canices Hall had a mixture of T-12 and T-8 flourescent lighting. It was proposed to install LED-Tubes for improved lighting in the space.

Insulation and Building Fabric upgrades

St. Canice’s opted to dry-line the main hall of the building. The rear snooker rooms were insulated used cavity wall pumped insulation. 300-mm of attic insulation was also added to the Main Hall, with roof vents. The back door was previously in bad repair and was replaced. As a result the centre now has wheelchair access which allows additional community members to use the facility.

Results

Since the upgrade the role of the centre has changed somewhat, with office space being added in one of the rear room, which has increased footfall. Based on the initial period of monitoring from December 2013-April2014, there was a 4% cost reduction and 13% usage reduction. If usage had continued as such it was expected that there would have been an overall 11% annual energy savings a result of lighting upgrades. There was a 32% reduction in oil usage at the site as a result of the insulation upgrades.

St Canices 1

Figure 1 St. Canices Hall During Upgrade

St Canices 2

Figure 2 Post Upgrade

 

St Canices 5

 

St Canices 6

 

St Canices 7